Scope of Work
The scope includes design, engineering, procurement, supply, fabrication, insurance, transportation, storage, construction, erection, installation, statutory approvals, testing, commissioning, sustained load test, performance guarantee test run, project management, and handing over of the Cooling Water System and related facilities on a turnkey EPC basis.
Go/No-Go Score
Risk Analysis
Top 3 Risks
AI Synopsis
Active Members
AI Synopsis
Active Members
| Topic | Page No. | Section | Clause | Data & Remark |
|---|---|---|---|---|
| Bid Bond | Page 9 | APPENDIX-1 TO ITT | 1.1.1, 1.1.2, 1.1.3, 2, 3.2, 3.3 | Bidders must meet technical, financial, and general criteria. Download BOT contract and project. |
| Eligibility Criteria | Page 17, 18, 37 | Eligibility Criteria | 8.1.1, 8.1.2, 8.2, 8.3, 8.3.b | Scope includes complete turnkey EPC for Cooling Water System at KSTPS Kota Unit# 5. |
| Scope of work | Page 6, 15 | Brief Scope of Work | 2.0 | The project site is located at KSTPS Kota, Rajasthan. Submit all documents before the deadline to avoid disqualification. |
| Location | Page 15 | INTRODUCTION | 1.2 | RRVUNL is the employer for this tender. Ensure all communications and submissions are directed to the specified office. |
| Employer/Owner | Page 6, 7 | Invitation for Bids (IFB) | 6.1, 6.2, 6.3 | Bids must be submitted online and include physical documents. Submit all documents before the deadline to avoid disqualification. |
| Bid Submission Details | Page 8 | Invitation for Bids (IFB) | Completion period is 30 days post-LOI or 15 days post-Work Order, whichever is earlier. | |
| Completion Period | Page 16, 36 | TIME SCHEDULE | 8.0, 8.1, 8.1.1, 8.1.2 | Bidders must meet PQR to qualify for evaluation. Technical criteria include experience with EPC projects and specific financial thresholds. |
| Bid Evaluation Criteria | Page 37 | Bid Evaluation Criteria | 3.2.d | The pre-bid meeting is crucial for bidders to clarify project requirements. |